PM Knowledge Center
Knowledge is either what you know or where to find it.
Risk analysis
An introduction to risk management
Since uncertainty is what typifies projects in progress, risk management is key to the success of a project. A technique known as Schedule Risk Analysis connects the risk information of project activities to the baseline schedule and provides sensitivity information of individual project activities as a way to assess the potential impact of uncertainty on the final project duration. The protection of a project's deadline using a technique called Critical Chain/Buffer Management assures that delays in project activities are captured by buffers that are cleverly inserted into the project baseline schedule.
The analysis of a project schedule's risk and its management through the use of detailed risk information and the incorporation of buffers is key to the success of a project. However, risk management is not a goal in itself, but rather it serves as a tool to improve and steer the project control phase (see "Dynamic scheduling: An introduction to project control"). Indeed, the combination of the baseline schedule (see "Dynamic scheduling: An introduction to baseline scheduling") and the risk information should be interpreted and used as a point-of-reference to reveal threats and opportunities during the project progress.
Schedule risk analysis
- Monte-Carlo simulations: How to imitate a project's progress?
- Monte-Carlo simulations: Linking critical path schedules to project control
- Project risk: Statistical distributions or single point estimates?
- Schedule Risk Analysis: How to measure your baseline schedule's sensitivity?
- Schedule Risk Analysis: Measuring the time sensitivity of an activity
- Time sensitivity measures
- Measuring time sensitivity in a project: The criticality index
- Measuring time sensitivity in a project: The cruciality index (Pearson's product-moment)
- Measuring time sensitivity in a project: The cruciality index (Kendall's tau rank correlation)
- Measuring time sensitivity in a project: The cruciality index (Spearman's rank correlation)
- Measuring time sensitivity in a project: The schedule sensitivity index
- Measuring time sensitivity in a project: The significance index
Buffer management
- Critical Chain/Buffer Management: Protecting the schedule against project delays
- Aggressive activity time estimates: Protecting against activity delays
- Critical Chain/Buffer Management: (Dis-)advantages of scheduling projects as-late-as-possible
- Critical Chain/Buffer Management: Adding buffers to a project schedule
- Sizing CC/BM buffers
- Critical Chain/Buffer Management: Sizing project and feeding buffers
- Sizing CC/BM buffers: The cut and paste method
- Sizing CC/BM buffers: The root squared error method
- Sizing CC/BM buffers: The adaptive procedure with density
- Sizing CC/BM buffers: The adaptive procedure with resource tightness
- Critical Chain/Buffer Management: Inserting buffers in a resource-constrained schedule
- Inserting buffers in a schedule: The problem with resource conflicts
